The stone wall on west side of the dam was rebuilt and extended 100 feet to connect to the northern shoreline. Soil that had migrated into the pond with each overtopping was recaptured and the inner section of the dam was excavated and filled with stones wrapped in geotech fabric. The dam surface was restored to its original height and slightly contoured to allow for runoff. The decayed bridge over the spillway was removed and the bridge beneath was restored with new handrails added.

Damage to the dam caused by overtopping and neglect

Completed repair of dam walls and hardening of dam surface

Recapturing soil that washed into the pond

Rebuilding the dam wall

Rebuilding the dam walls

Bridge over the sluice gate decaying

New bridge with handrails for better access